Adani to finish 1,000 MW transmission line to Mumbai by Dec 2022


Picture Supply : PTI

Adani to finish 1,000 MW transmission line to Mumbai by Dec 2022

Adani Transmission Ltd (ATL) on Sunday affirmed that will probably be capable of execute a transmission line and sub-station venture at suburban Vikhroli which can improve the facility provide by 1,000 MW to the monetary capital, by the tip of subsequent 12 months, as per the mandated deadline for it.

In a assessment assembly taken following final Monday’s energy outage, Maharashtra Chief Minister Uddhav Thackeray had requested all stakeholders to expedite the venture by adhering to the timelines.

Trains had been caught on tracks, companies affected and do business from home staff impacted because the monetary capital plunged into darkness final Monday that lasted as much as 14 hours in some pockets.

“Adani is dedicated to finishing the Kharghar-Vikhroli transmission line venture throughout the timeline set by Thackeray,” a spokesperson for Adani Group mentioned in an announcement.

Within the assertion, ATL mentioned there will probably be development in energy load within the megapolis and the mismatch between technology and cargo development, it’s now dedicated to executing two essential transmission tasks that might assist channelise extra energy to Mumbai.

These capability enhancement tasks will create a further transmission capability of 1,000 MW every, thereby easing the prevailing transmission corridors, it added.

It contains the Kharghar-Vikhroli 400/220 kV EHV transmission line venture, which can add a 1,000 MW energy provide hall and also will be Mumbai’s first 400 KV Substation.

A latest information report had mentioned that there was a dispute between Tata Energy and ATL which has now been resolved with the previous agreeing to offer land for the venture.

The venture was reportedly permitted in 2009 and awarded to ATL in 2019. ATL on Sunday mentioned it has already positioned orders for all essential tools and repair contracts, that are important for venture completion, together with towers and insulators. It has additionally accomplished 80 per cent of engineering and is working with authorities to get possession of land parcels at Kharghar and Vikhroli.

Other than the Vikhroli-Kharghar line, a second venture includes an 80-km hyperlink between Maharashtra State Electrical energy Transmission

Firm’s (MSETCL) 400 kV Kudus & Adani Electrical energy Mumbai’s (AEML) 220 kV Aarey EHV Substation which will probably be a primary of its type underground excessive voltage DC cabled system that may get a further 1,000 MW of energy.

Adani has initiated land procurement, accomplished survey works, filed functions for Regulatory, proper of approach and different statutory clearances, awarded consultancy contracts for system research and is within the means of elevating capital and finalizing awards for venture execution, the assertion mentioned. 